Resources represent capacity. They represent a machine, a worker or a group of workers, or some logical limits.
Operations will consume capacity using loads.
Different types of resources exist:
Fields
Field | Type | Description |
---|---|---|
name | non-empty string | Name of the resource.
This is the key field and a required attribute.
|
description | string | Free format description. |
category | string | Free format category. |
subcategory | string | Free format subcategory. |
owner | resource | Resources can be organized in a hierarchical tree.
This field defines the parent resource.
When an operation loads a resource which has members, the
planning algorithm will select one of the child resource.
|
members | list of resource | Resources can be organized in a hierarchical tree.
This field defines a list of child resources.
|
location | location | Location of the resource.
Default is null.
The working hours and holidays for the resource are taken
from the ‘available’ calendar of the location.
|
maximum | double | Defines the maximum size of the resource.
The default value is 1, i.e. a resource that can handle
1 operationplan at a time (provided of course that this
operationplan requires 1 unit on the resource).
A problem is reported when the resource load exceeds
than this limit.
This field is ignored on resource of type buckets and infinite.
|
maximum_calendar | calendar | Refers to a calendar storing the available capacity.
Use this field when the resource size is varying over time.
If this field is populated, the field maximum is ignored.
On resources of type buckets this calendar defines the
time buckets as well as the maximum quantity per time bucket.
This field is ignored on resources of type infinite.
|
cost | double | The cost of using 1 unit of this resource for 1 hour.
The default value is 0.
|
detectproblems | boolean | Set this field to false to suppress problem detection on
this resource.
Default is true.
|
maxearly | duration | Time window before the ask date where we look for available
capacity.
The default value is 100 days.
|
loads | list of load | Defines the capacity of the operations. |
loadplans | list of loadplan | This field is populated during an export with the plan
results for this resource. It shows the resource load
profile.
The field is export-only.
The description of the loadplan model is included in the
section on operationplan.
|
level | integer | Indication of how upstream/downstream this entity is
situated in the supply chain.
Lower numbers indicate the entity is close to the end
item, while a high number will be shown for components
nested deep in a bill of material.
The field is export-only.
|
cluster | integer | The network of entities can be partitioned in completely
independent parts. This field gives the index for the
partition this entity belongs to.
The field is export-only.
|
setup | non-empty string | The name of the current setup of the resource, ie the setup of the resource at the start of the planning horizon. |
setupmatrix | setupmatrix | The name of the setup matrix which specifies the changeover times between setups. |
hidden | boolean | Marks entities that are considered hidden and are normally not shown to the end user. |
action | A/C/AC/R | Type of action to be executed:
A: Add an new entity, and report an error if the entity
already exists.
C: Change an existing entity, and report an error if the
entity doesn’t exist yet.
AC: Change an entity or create a new one if it doesn’t
exist yet. This is the default.
R: Remove an entity, and report an error if the entity
doesn’t exist.
|
A default resource is constrained with a maximum load size. The resource size defines how many operations that can use the resource in parallel.
For detailed planning and scheduling this is the most suitable resource type. E.g. A resource that can run 2 jobs at the same time.
No fields are defined in addition to the ones listed above.
A bucketized resource is constrained with a maximum load quantity per time bucket.
For master planning and rough cut capacity planning this is most suitable resource type. E.g. A resource that can produce 1000 units per week
No fields are defined in addition to the ones listed above, but the maximum_calendar field must is be specified.
An infinite resource has no capacity limit. It is useful to monitor the loading or usage of a resource without constraining the plan.
The fields ‘maximum’ and ‘maximum_calendar’ are unused for this resource type.
Example XML structures
Adding or changing a resource
<plan>
<resources>
<resource name="machine X">
<maximum_calendar name="capacity calendar for machine X" />
</resource>
<resource name="machine Y">
<maximum>2</maximum>
</resource>
</resources>
</plan>
Deleting a resource
<plan>
<resources>
<resource name="machine X" action="R"/>
</resources>
</plan>
Example Python code
Adding or changing a resource
cal = frepple.calendar(name="capacity calendar for machine X")
res_X = frepple.resource(name="machine X", maximum_calendar=cal)
res_Y = frepple.resource(name="machine X", maximum=2)
Deleting a resource
frepple.resource(name="machine X", action="R")
Iterate over resources, loads and loadplans
for r in frepple.resources():
print "Resource:", r.name, r.description, r.category
for l in r.loads:
print " Load:", l.operation.name, l.quantity,
l.effective_start, l.effective_end
for l in r.loadplans:
print " Loadplan:", l.operationplan.operation.name,